Solar Anti-Backflow Wiring: Connecting an Energy Meter to an Inverter

Short answer: For anti-backflow control, fit the energy meter's CT clamps on the grid connection point so they measure all power flowing to and from the grid, wire the meter to the inverter over RS485 Modbus RTU or over local Wi-Fi (MQTT, HTTP or Modbus TCP), and check that exported power reads as negative. When total active power is negative, the inverter lowers its output within 2 seconds or charges the battery first.

How does anti-backflow control work?

Where should the CTs go?

The CTs must see the net flow between the site and the grid. Put them on the live conductors of the main grid feed, upstream of the loads and of the point where the inverter's output joins the installation. A CT placed on the inverter's own output measures solar production, not the grid exchange, and cannot control export.

How do I wire the meter?

  1. Switch off the supply and confirm there is no voltage.
  2. Mount the meter on the DIN rail and connect the power supply and the voltage reference as shown in its quick start guide.
  3. Clamp the CTs on the grid feed and plug their cables into the meter's CT terminals.
  4. Follow the CT arrow direction given in the quick start guide of your model. On the single-phase PC4711 the arrow points towards the load.
  5. Connect the communication path to the inverter (next section).
  6. Switch the supply on and read the meter.

Which communication method should I choose?

The PC4713-W-485 provides both: Wi-Fi 2.4 GHz (HTTP, MQTT, Modbus TCP) and an RS485 port (Modbus RTU). Its data refresh is 50 ms and the Modbus RTU response time is up to 50 ms. The PC4713-W variant has Wi-Fi only. Protocol documents are available from OWON sales on request.

MethodMediumBest for
Modbus RTU (RS485)WiredStable network, strong anti-interference, low latency, long distance and high-frequency polling
MQTT / HTTP / Modbus TCPLocal Wi-FiNo cloud latency and no wiring cost; short-distance, high-frequency communication where wiring is inconvenient

How do I check the installation?

  1. With the inverter running and a load switched on, read the meter's real-time active power. Importing from the grid should read positive.
  2. Reduce the site load or increase the solar output until surplus is available. Exported power should read negative.
  3. If the sign is the wrong way round, turn the CT clamps round and read again.
  4. Confirm that the inverter lowers its output, or charges the battery, when the reading turns negative.
  5. Record CT size, direction, phase and the communication settings.

Check the inverter manufacturer's documentation to confirm which meter protocol and which register map it reads, and follow your local grid code for export limits.

What are the benefits?

Related OWON products

OWON PC4713-W-485 Open API Smart Energy MeterOWON PC4713-W-485 Open API Smart Energy MeterDIN rail three-phase energy meter with Open API (Wi-Fi and RS485)Wi-FiRS485 / EthernetOpen API

Frequently asked questions

Where do I install the CTs for anti-backflow control?

On the live conductors of the grid connection point, so that the meter measures the net power exchanged with the grid.

Which OWON meter supports RS485 Modbus RTU for an inverter?

The PC4713-W-485 has an RS485 port with Modbus RTU and Wi-Fi with HTTP, MQTT and Modbus TCP.

How fast does the inverter react?

When total active power turns negative, the inverter reduces its output within 2 seconds, or stores the surplus in the battery first.

Does it work with three-wire delta systems?

The PC4713-W-485 does not support three-phase three-wire or delta systems. It supports single-phase, split-phase and three-phase four-wire.

Related guides

Last updated: . Published by Xiamen OWON Technology Co., Ltd., the manufacturer of the products described. Reviewed by David Huang, Product Manager.

Talk to OWON about your project

Tell us your application, target market and quantity. Our sales team replies with datasheets, protocol documents and pricing.

Send an enquiry WhatsApp +86 13159213403

Or email sales@owon.com